Finishing works at SP 65 Della Futa

Finishing works at SP 65 Della Futa

The provincial road 65 ‘della Futa’ is the main link between the urban area of Bologna and the municipalities of the Savena Valley. The contract involves the construction of the final section to complete the new road alignment connecting the Ponte delle Oche and Via Corelli in the Municipality of Bologna. “Among the main works to be carried out: a steel and concrete viaduct with 5 spans, totaling 263 meters in length, an artificial tunnel of approximately 100 meters crossing the Bologna-Firenze railway line, two roundabouts, and several environmental mitigation interventions, all designed to minimize impact on the surrounding urban context while keeping vehicular, railway, and pedestrian traffic active.

Project Details

Client:

Città Metropolitana di Bologna

Services performed:

Detailed design

Localisation:

Rastignano (BO)